Where should a mining contractor grow when its core market is under pressure?

Fix the cost base first, win the contracts that are actually open, and enter adjacent services through partnerships, in a set order. Cost is the one lever a contractor controls: in 2013 the largest players dug more coal, yet each tonne carried less work, and by December 2014 the benchmark coal price was 43% below its March 2012 level.

  • Role Business Analyst, management consulting team
  • Duration about 12 weeks, 2014
  • Scope Indonesia, mainly Kalimantan and Sumatra
  • Format anonymized public case

Largest contractors, 2012 to 2013

More coal mined, but roughly the same earth moved, so each tonne meant less overburden work.

Coal mined

+11%

Overburden moved

about flat

Strip ratio

BCM per tonne, approx.

-10%

Source: industry data and annual reports of the largest listed contractors, as compiled in the engagement fact base. Strip ratio fell for every major player in 2013.

The core is squeezed

Lower prices and lower strip ratios cut what owners will pay and how much earth-moving work each tonne creates.

Cost is the lever

Contractors do not set prices or strip ratios. About 70% of their operating cost sits in two lines they can manage.

Growth must be accessible

Chase contracts that are opening, services buyers can unbundle, and adjacencies in order of capability fit, with partners where capital is short.

The core business is squeezed from three sides at once

The client had to grow, yet the usual route, more fleet and more contracts, was getting less profitable. Three forces explain why.

Prices fell

The benchmark price dropped from US$112.87 per tonne in March 2012 to US$64.65 by December 2014. Owners passed the pressure on as rate cuts.

Less work per tonne

Owners cut strip ratios to lower their own cost. Overburden removal is a key contractor revenue driver, so revenue per tonne of coal fell.

Entrenched rivals

About 116 contractors compete, but the top seven hold roughly 60% of contracted production, often through long contracts and owner affiliation.

Exhibit 1. The benchmark coal price had already lost 43% by the time the report was written

Government reference price (HBA), US$ per tonne, selected months. The shaded part is after the report, shown for context.

After the report 04080120 112.9 81.8 80.3 64.7 (-43%) 53.5 (-53%) Mar 2012Dec 2012Dec 2013Dec 2014Dec 2015

Source: Ministry of Energy and Mineral Resources (ESDM), monthly HBA releases. Percentages are against March 2012.

What the contractor can and cannot change

Splitting margin into its drivers shows that the biggest pressures sit outside the contractor’s control. What remains is cost per BCM (bank cubic metre of earth moved).

Exhibit 2. Two drivers are set by owners and markets; the cost side is the contractor’s to manage

Contractor margin per BCM, broken into its drivers.

Marginper BCM moved Revenuevolume x rate Operating costper BCM Less overburden per tonne of coalStrip ratio about 9 to about 8 (2012 to 2013) Pressure on contractor ratesBenchmark price -43% (Mar 2012 to Dec 2014) Fuel, lubricants, repair and maintenanceAbout 70% of operating cost Labour, drilling and blasting, overheadsThe remaining 30% or so Set by owners and the market Within the contractor’s control: the target of cost leadership

Source: engagement analysis; cost split from competitor and interview benchmarking.

Four hypotheses structured the work

The team converted the problem into testable hypotheses and used interviews to confirm or reject each. The client also set a hard boundary: little capacity for extra investment or staff, so the strategy had to deliver maximum impact with minimum support, starting with quick wins.

H1. Cost leadership should come first

Supported

Owners were cutting strip ratios and pressing rates, while leading peers reported around 22% operating margin and cost cuts of up to 12% (about US$31M) over 2013 to 2014.

H2. Open contracts can be predicted

Supported

Windows opened at contract expiry, incumbent underperformance, or new concessions beyond incumbent capacity. Owner affiliation was the strongest predictor of who held the work.

H3. Differentiation needs full pit-to-port ownership

Partially rejected

Buyers could procure drilling and blasting, hauling, and ports separately, and specialists had succeeded by focusing on one segment. With limited capital, partnership beat ownership.

H4. Construction is the logical adjacency

Supported, in sequence

Only two of the six largest contractors had meaningful construction exposure. Mining infrastructure transfers best; piling and EPC need partners, references, and engineering depth.

Evidence base: 50+ stakeholders (3+ experts and associations, 10+ mine owners, 15+ contractors, 5+ traders, 10+ adjacent-industry companies, 5 to 10 construction participants), plus secondary research and competitor benchmarking.

Cost per BCM is the one lever in the contractor’s hands

Cost leadership does two jobs at once. It protects margin when owners cut rates, and it lets the contractor quote lower than rivals when bidding for new contracts. The shift is in the operating objective: from the highest production to production at the lowest cost per BCM.

Exhibit 3. About 70% of operating cost sits in two lines, so three levers address the bulk of the cost base

Operating cost structure and the levers that act on it.

Burn less fuel per BCM

A fleet management system dispatches trucks to match excavators and cuts idle time and wasted haul cycles.

Tracked by: fuel per BCM, dispatch compliance, utilization

Keep assets running longer, for less

Component rebuild and life-extension programs, parts stocked by criticality, and planned shutdowns. Peers stretched asset life by 1 to 3 years.

Tracked by: maintenance cost per hour, physical availability

Make cost everyone’s job

Activity-based costing per BCM, KPIs cascaded to site teams, incentives tied to cost-down, and centralized supply chain.

Tracked by: cost per BCM, improvement pipeline, owner per cost driver

Source: competitor benchmarking and primary interviews; operating cost split as described in the engagement recommendations.

Grow where the contractor can win without a price war or a large cheque

Every option was screened on seven questions: Is the market attractive? Do capabilities transfer? Can the client reach the customer? How much capital is needed? How fast does it pay back? Can it win beyond price? What is missing to execute?

1. Pursue contracts that are opening, not every concession

Exhibit 4. Screening narrows the market to accounts with a real window to switch

Account-level screening logic. No counts or names are disclosed.

All concessions in scope
Not locked by an affiliated contractor (affiliation is the strongest barrier)
Financially able to fund or contract the work
A window is open: contract expiring, incumbent underperforming, or new project
Contract expiryAn expiring contract creates a natural moment to bid.
Incumbent underperformanceDissatisfied owners listen to a better, cheaper offer.
New or expanding concessionsGreenfield and expansions can exceed what the incumbent can handle.

Source: customer-screening logic developed during the engagement, validated through owner and contractor interviews.

2. Unbundle the pit-to-port chain and focus on three links

Buyers can purchase services separately. The question is which links are worth entering. The answer: those where rivals are not already fighting on price, and where a partner can share the capital.

Exhibit 5. Three links offer room to differentiate; the middle of the chain is a price war

Coal mining services value chain, from pit to port.

Drilling and blastingFocus
Overburden removalPrice war
Coal gettingPrice war
CrushingNot a focus
HaulingFocus
Port managementFocus
Drilling and blasting: supply is the bottleneckAmmonium nitrate depended on imports until 2012, and large players locked in long-term supply, so securing a supplier partner opens the door.
Hauling: a big cost line without scale for small minesClusters of nearby mines can share fleet and roads. Local contractors operate while the client brings fleet management and best practice.
Port management: capacity is scarceMost terminals are private to large players, only three common-use terminals handle large volumes, and the government planned 14 more terminals.
Overburden removal and coal getting: where price is the only weaponAbout 116 contractors compete here. Cost leadership (Exhibit 3) is what works in this part of the chain.

Source: competitor and customer interviews, port and ammonium nitrate market analysis. Crushing was not seen as a competitive focus in the benchmark.

3. Enter adjacent markets in order of capability fit

Exhibit 6. Mining infrastructure and selected minerals first; specialist construction and EPC only after capability gates

Adjacencies by capability gap and time to impact.

Near termLonger term Mining infrastructure Other minerals Civil works and piling Structural steel and EPC Cement Deprioritized: little overburden work, entrenched incumbents Smaller capability gapLarger capability gap

Source: capability-adjacency assessment against assets, people, customer access, capital, and execution risk.

Six pathways in a set order keep the core strong before anything new is funded

The order follows speed and effort: quick, low-capital moves first, anything that needs new capabilities last.

Exhibit 7. Each pathway has a reason, a timeframe, and an effort level

Growth portfolio for the client.

1

Cost leadership

Prices are falling and cost is the one lever the contractor controls.

ImmediateLow effort
2

Contract capture

Open windows at expiring or underperforming contracts let a stronger contractor replace weaker ones.

ImmediateMedium effort
3

Selective vertical integration

Unbundled drilling and blasting, hauling, and port services differentiate without owning the whole chain.

About 1 yearMedium effort
4

Value-chain partnerships

Tie-ups with traders give mine owners a route to market and give the contractor a reason to be chosen.

ImmediateLow effort
5

Other minerals

Outsourced activities such as drilling, overburden, loading, and hauling match existing capabilities.

1 to 2 yearsLow effort
6

Construction and EPC

A market growing 8 to 13% a year, but it needs credentials and new capabilities, so it is staged.

PhasedHigh effort

Shading: green deepens with speed; amber deepens with effort. Source: strategic recommendations of the engagement.

Exhibit 8. Three horizons: defend, expand selectively, then transform

Sequencing of the six pathways. Investment gates differ by horizon.

0 to 12 monthsDefend and strengthen
1 to 2 yearsExpand selectively
Longer termTransform
1. Cost leadership
Build the cost program
Sustain and extend to every site
2. Contract capture
Qualify accounts, bid
Convert and extend contracts
3. Vertical integration
Prepare licences, suppliers
Pilot, then scale
4. Partnerships
Trader tie-ups
Operational JVs
5. Other minerals
Outsourced activities
6. Construction, EPC
Mining infrastructure, civil works
Piling, structures, EPC after gates
Main effortPreparing or continuing

How the strategy could be governed

Author’s post-engagement synthesis. This scorecard and the risk list were prepared afterwards to show how the strategy could be run. They were not part of the original deliverable.

InitiativeLeading indicatorsOutcome KPIsGate
Cost leadershipImprovement pipeline, cost-driver owners, maintenance actions closedCost per BCM, fuel per BCM, maintenance cost per hourMonthly operating review
Contract captureQualified accounts, expiries tracked, decision-maker accessPipeline value, bid conversion, marginBid or no-bid committee
Drilling and blastingLicence readiness, supplier agreementsProject margin, utilization, safety incidentsPilot, then scale
HaulingCluster participation, road agreements, fleet planCost per ton-km, truck utilizationCluster business case
Port servicesTerminal access, anchor customerThroughput, turnaround, demurrage exposureAnchor-volume threshold
Construction adjacencyPartner secured, critical hires, referencesBacklog, margin, on-time delivery, reworkCapability-stage gate
Management dilutionCap active initiatives and sequence investments.
Utilization riskBuy fleet only against contracted or highly qualified volume.
Capability overreachGate EPC on engineering depth and reference projects.
Partnership governanceAgree decision rights, performance clauses, and exit terms.
Customer concentrationSet portfolio limits and diversify accounts in stages.
Data qualityStandardize KPI definitions and keep auditable baselines.

In hindsight, the squeeze thesis held through 2017, but a single-point forecast missed the upswing

This section is an observation made years later, not a claim about project impact. It compares the base-case forecast in the original analysis with what the data later showed.

Exhibit 9. Output went flat for four years, then outgrew the 2020 forecast by 12%

Indonesian coal production, million tonnes (Mt), actual versus the forecast used in the engagement.

Actual (ESDM)Forecast in the engagementFlat period, 2014 to 2017

Sources: actual production from ESDM data as reported in ministry releases and press (2006 to 2011 figures matched the engagement data; 2012 and 2013 were later revised upward from 383 and 421 Mt to about 412 and 474 Mt); forecast from the original analysis.

What a reader should take away, and what this case does not claim

Result integrity. The engagement produced strategic outputs and decision value. It did not document realized revenue or cost savings after implementation, so none are claimed here. Market data reflects the 2014 project period. Competitor economics relied on triangulation because private-company data was incomplete, and interview findings reflect stakeholder perspectives. Confidentiality. Client identity, named partnership or acquisition targets, personal contacts, tender details, exact cost benchmarks, and confidential financial assumptions are excluded.